Call to fix Ormskirk flooding spot after ‘responsibility finally clarified’
Progress is finally being made over a ‘long-running saga’ about Ormskirk flooding and responsibility for a waterway debris screen near Coronation Park, councillors have been told.
The latest full meeting of West Lancashire Council had an update on flooding in the Halsall Lane area over years, and clarifying ownership and maintenance responsibility for a debris screen at Hurlston Brook, near the A59 County Road.
A new report for councillors said there were ‘significant events’ in 2001, 2002, 2008, 2011, 2012 and 2015, plus storms in January 2025 again caused ‘property flooding, boat rescues and deep standing water’ around Halsall Lane.
In recent months, West Lancashire Council has held talks with Lancashire County Council and the Environment Agency.
It also reviewed the planning history of a housing development at the former Comrades Club site, called Coronation Court.


At the latest meeting, councillors were given an update report, outlined by Labour Coun Gareth Dowling, the deputy council leader.
He said: “Residents or this council cannot just take responsibility for things like this. What next – the M6? We’ve put a lot of work into this. It’s been going on for years. We know who is responsible. The county council just needs to step up.”
The report said the debris screen at the A59 culvert inlet was funded and installed by developer McCarthy and Stone Retirement Lifestyles to resolve an objection in the past from the Environment Agency. But McCarthy and Stone had no ongoing duty to maintain or repair the screen.
Over time, different people including West Lancashire Council staff, residents and the Environment Agency had ‘intermittently’ cleared the screen through goodwill. But this did not mean they had formal responsibility for it.
This summer, West Lancashire councillors said some county council staff recently did clearance work there, suggesting possible acceptance of county responsibility. Then in November, the county ‘acknowledged the complexity of the issue’ and said its legal and technical teams were looking at the issue, the report added.
Speaking at the meeting, Our West Lancashire (OWL) Coun Gordon Johnson said: “This has been quite a hot topic for me, as a county councillor too. I’ve been in weekly contact with the county on this and I’m aware it has taken interim responsibility for the screen. But I also know the county has been working on other flooding attenuation work in the borough. There are issues not just with the screen.”
Labour’s Nikki Hennessy welcomed the update report, saying: “This is really in-depth. A lot of us were on the streets there, mopping-up and comforting residents during the flooding of early 2025. But there was nobody from the county council there on January 1. Nobody from the county attended until January 2. Can we ensure that we have contact details for the county – for residents and borough councillors.”
Conservative John Howard asked if West Lancashire Council had managed to employ a drainage engineer. An officer said temporary arrangements were in place and there had been difficulties with recruitment.
OWL Coun Neil Furey added: “This saga is longer than TV’s Dallas. This report shows it’s still an ongoing issue. There are still residents clearing the screen after heavy rain and issues about who is attending and how. It looks bad on both councils. If ever you needed an argument for local government reform, this is it. It’s a spat and I’m sick of it.”