Work has resumed on the A585 traffic improvement project north of Blackpool.
From Monday, January 10 until Sunday, January 23, there will be some changes to the traffic lights and road system between Skippool and Windey Harbour and National Highways is warning drivers to prepare.
Two-way temporary traffic lights and a lane closure to allow services diversions will be in place at Lodge Lane as workers return after the Christmas break.
Mains Lane will have narrow lanes for the same reason, while Skippool Bridge will have narrow lanes to allow construction work to continue.
Most Popular
-
1
Six-mile tailbacks on M6 southbound north of Preston after collision closes a lane
-
2
REVEALED: The Preston city centre facelift plan that could leave some areas unrecognisable in 10 years' time
-
3
Newly-wed who lost wife to cancer only 13 weeks after their wedding makes £50,000 donation to charity in her memory
-
4
Police appeal after attempted robbery of woman on Lancaster canal towpath
-
5
Chorley man wanted in connection with threats to kill arrested moments before he was about to indulge in meal at McDonald’s in Blackburn
At Skippool Roundabout, there will be narrow lanes, with one lane closed on Amounderness Way eastbound.
One lane will also closed on the approach to the roundabout northbound on Breck Road from Poulton-le-Fylde.
However, both Lanes open on the approach to the roundabout on the westbound of Mains Lane.
Drivers are warned to keep an eye out for construction traffic crossing Garstang Road East.
Garstang New Road (east-bound) and Windy Harbour junction, will see no changes to the road layout for the two week period as the £150m project continues to try to reduce traffic congestion.