Lasting between one day and ten days, the projects include temporary traffic lights and carriageway incursions to allow work to be completed.
Motorists are advised to avoid these areas if they can or to plan their journey to give themselves more time.
Below is a full list of the affected roads, how long the work is scheduled to last and the reason for the roadworks (ordered by start date, from Monday to Friday.)
![What: Some carriageway incursion
Why: [New service connection] Excavate in footway to clear blockage for customer connection
When: April 3- April 5](https://www.lep.co.uk/webimg/b25lY21zOmY4MzM4MzQwLTg0NjYtNDY1ZS05Zjc0LWY0OWI0MDA1OGNmMTplZDUwNDBkMC0yNWVlLTRiYmYtYjg1Yi1kNjMzYmQ2ZTUyNTA=.jpg?crop=4:3&trim=&width=640)
13. Janice Drive, Fulwood
What: Some carriageway incursion Why: [New service connection] Excavate in footway to clear blockage for customer connection When: April 3- April 5 Photo: Google Maps
![What: Some carriageway incursion
Why: [Utility repair and maintenance works] Erect Pole in Verge and a pole in footway
When: April 3- April 5](https://www.lep.co.uk/webimg/b25lY21zOjlhMmFiOTNkLTAzMGItNGEwNi04YWM3LThhNGNjMDZlMTVkZTphYjAyYWFlNC01OTY2LTQzNDYtYmFhZC1lMmQzZmI4YzE2ZTM=.jpg?crop=4:3&trim=&width=640)
14. Ribbleton Avenue, Preston
What: Some carriageway incursion Why: [Utility repair and maintenance works] Erect Pole in Verge and a pole in footway When: April 3- April 5 Photo: Google Maps
![What: Give and take
Why: [Statutory infrastructure works] laying grain network. Approx 150m. Crossing side of 42&78. f/w 2 box o/s 66.
When: April 3- April 18](https://www.lep.co.uk/webimg/b25lY21zOjNlMGMzMDJiLTY3MGMtNGY5Ni1hM2I2LTlkOTNjN2VlMjNhODoyMDM3MDgxNi1jMGZiLTQ0ZWUtYTVjZS1kMTg3Yzc2YjI2OWM=.jpg?crop=4:3&trim=&width=640)
15. Henderson Street, Preston
What: Give and take Why: [Statutory infrastructure works] laying grain network. Approx 150m. Crossing side of 42&78. f/w 2 box o/s 66. When: April 3- April 18 Photo: Google Maps
![What: Some carriageway incursion
Why: [Utility repair and maintenance works] Open cut excavation is required to repair stop tap in footway
When: April 4- April 6](https://www.lep.co.uk/webimg/b25lY21zOjk2NjE5ZjI2LTEyNGItNGRiNC1hZDMyLTVmNjk5Y2U2ZDNhZDpjZTQ3YzRkMC1lOTAzLTQ0Y2EtOTY0Yi0zYTQ3ZGZmMzRjMTk=.jpg?crop=4:3&trim=&width=640)
16. Banks Road, Fulwood
What: Some carriageway incursion Why: [Utility repair and maintenance works] Open cut excavation is required to repair stop tap in footway When: April 4- April 6 Photo: Google Maps