Why roadworks due to take place in Longridge will take six months

Longridge roads will be dug up to install high voltage electrical supplies to new homes estates - and the disruption will last six months. Here’s what’s happening.

A schedule of road works which will stretch until April next year have been announced in Longridge.

The work, which will see the installation of a new high voltage electrical supply for the Barratt David Wilson Homes development at Whittingham Lane/Cumeragh Lane, will be undertaken by contractors PD Daly.

A letter sent to local residents and businesses said: “ The point of connection for the works is Fell Brow, Longridge. From there the cable route runs from Longridge centre, through Whittingham and Cumeragh, to the development.’ The letter includes a drawing of the route.

The letter explains the work will be delivered in eight consecutive phases, working from Fell Brown toward the development with ‘any excavation opened over a weekend will be backfilled and permanently reinstated before workers leave the site at approximately 4.30pm on Sundays.

  • The first phase starts on October 19 and is due to be completed on October 15.
  • Phase 2: 16/11/26 - 29/11/26
  • Phase 3: 11/30/26-24/12/26
  • Phase 4: 04/01/27-31/01/27
  • Phase 5: 01/02/27 - 21/02/27
  • Phase 6: 22/02/27-28/03/27
  • Phase 7: 29/03/27 - 18/04/27
  • Phase 8: Week commencing 12/04/27 until the high voltage connection is turned on

Roadworks in Longridge will last until April 18, 2027placeholder image
Roadworks in Longridge will last until April 18, 2027 | Iconic Media

PD Daly say all efforts will be made to reduce impact and residents, businesses and road users with access to properties maintained throughout.

  • Another busy route in Preston will see 11 weeks of roadworks begin next month. Disruption is expected on the affected stretch of Longridge Road around Roman Way Industrial Estate in Ribbleton from October 5 to December 23. Four way traffic signals will manage traffic flow while crews carry out resurfacing and drainage works, which will be completed in two phases.
  • And The M6 northbound is closed overnight between junctions 32 (Broughton) and 33 (Lancaster South) on Thursdays and Saturdays up to October 29. It’s for work as part of a bridge maintenance work programme including waterproofing and resurfacing of the carriageway as well as repairs to Whittingham Lane bridge. A temporary lane closure is in place daily during the works but to help keep traffic moving during peak periods, traffic management will be removed on Thursday nights and reinstalled on Saturday nights.
News you can trust since 1886
Follow us
© 2026 Iconic Media Group Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice