Councillor’s fire safety fears over new Preston battery storage farm next to the M6
and on Freeview 262 or Freely 565
Preston City Council’s planning committee gave the go-ahead to the proposal for a plot of land off Green Lane in Barton, where 64 storage units are now set to spring up. They will enable power generated from green sources like wind and solar to be saved for use during periods of high demand.
However, there was concern amongst some members over the risk of a fire at the 45 megawatt development, which will sit right alongside the M6.
Advertisement
Hide AdAdvertisement
Hide AdOne of them – Cllr Harry Landless – said he was surprised that there had not been any local opposition to the plans given the possibility of what he described as a “doomsday scenario”. Not a single public comment was submitted to the authority in response to the proposed project, situated to the north of Mount Pleasant Farm.
The meeting heard that the technology involved was “novel” and council planning case officer Jonathan Evans said that there was “the potential risk of fire”.
Lancashire Fire and Rescue Service (LFRS) recommended that the applicant – Baron Battery Storage – produce a risk reduction strategy and the committee was told that the resultant document was considered by the fire brigade to be “satisfactory”.
However, LFRS noted that an “outline battery fire safety management plan” had not been prepared “by an accredited professional”, according to papers presented to the committee.
Advertisement
Hide AdAdvertisement
Hide AdIn its response to the proposal, the brigade said that it would “expect that safety measures and risk mitigation [to be] developed in collaboration with the [fire] service”.
Members were told that the council was unable to impose conditions based on comments and recommendations from LFRS, as it was not a statutory consultee – but Mr. Evans said that the company had shown that it was “willing to engage” with the organisation.
Amongst the safety measures the fire service suggested was the inclusion of automatic fire detection and suppression systems in the development design. It also told the applicant to factor in “prevailing wind directions” when siting the equipment in order “to minimise the impact of a fire involving lithium-ion batteries due to the toxic fumes produced”.
Cllr Landless said that he found the proposal “very worrying” – and predicted a “proliferation of these [sites] all over our countryside”.
Advertisement
Hide AdAdvertisement
Hide Ad“If this works here, there will be many more sites around rural north…and rural east Preston, where farmers – or the people who own the land – know that they can’t get [permission] for housing developments…so this will be the next best thing,” he said.
Fellow committee member Stephen Thompson said that an industrial site in open countryside “shouldn’t be allowed” – and also expressed concern over what he said was technology that was “very early on” in its development.
National Highways had initially placed a holding objection on the plans – in part because of the potential impact of a fire on the safe operation of the M6. They raised concerns that if the battery technology caught fire, it would release black toxic smoke, which would be blown towards the motorway by the prevailing eastward winds – and require the route to be shut.
However, after the applicant engaged with roads bosses and produced a fire safety strategy, National Highways withdrew its objection – subject to the submission of an emergency response plan.
Advertisement
Hide AdAdvertisement
Hide AdCllr Jennifer Mein said she was “disappointed” that the fire service was not a statutory planning consultee, especially as battery storage facilities were likely to become “more and more common”.
The council’s development management team leader Phil Cousins that some of the health and safety concerns raised at the committee could be dealt with under building regulations even if they were beyond the scope of the planning department
Meanwhile, committee member Fiona Duke said that developments like the one being proposed were needed in order to keep the lights on – even if the countryside location was one that caused some of her colleagues to baulk.
“For me, this is really species-poor grassland [and] they’re building a really effective screen. It is right next to a motorway, so it’s not a pristine habit or landscape,” Cllr Duke added.
Advertisement
Hide AdAdvertisement
Hide AdNobody from – or on behalf of – Barton Battery Storage addressed the committee, but in documents submitted with its application, the company said that “the risk of major accidents is very low” and that there was “no risk to human health” as a result of its plans.
The application was approved by a majority, with Cllrs Landless and Thompson voting against.
The scheme is contrary to some elements of local planning policy, which would usually preclude development of this scale in open countryside. However, both Central Lancashire’s planning strategy and national planning policy guidance support renewable and low-carbon energy projects, provided that they cause no unacceptable impact on the character of the landscape and that the adverse effects of any development do not outweigh its benefits.
As well as the battery storage units, transformers, a switching unit, substation control room and other associated infrastructure will be installed on the 1.1 hectare plot.
Advertisement
Hide AdAdvertisement
Hide AdEach battery unit will be housed in a metal box 3.1 metres high, 2.4 metres wide and six metres long. They will sit on feet raised above ground level by 0.2 metres. The switch gear unit will take the form of a metal container, which will measure 3.1 metres by 12.2 metres and have a maximum height above ground level of 4.1 metres.
For security, six infrared CCTV cameras will guard the site, palisade fencing will encase the plant equipment and a four-metre high acoustic fence will surround the battery compound.
The committee meeting heard that while a battery storage scheme had been built at Red Scar Business Park in 2019, that development included a gas peaking power plant, meaning that the facility now approved in Barton was the first sole battery storage site in Preston.