'So proud to deliver this monumental project' - this is what's left to do before Preston Tram Bridge reopens
After 18 months on site, staff at Eric Wright Civil Engineering are getting ready to put the finishing touches to Preston’s new Tram Bridge.
The Bamber Bridge-based company has announced that it will soon begin reinstating the area and resurfacing the Old Tram Road ahead of the grand opening in spring. They say these efforts “will restore the route and provide a welcoming approach to the new bridge.”
The final three sections of the 150-tonne bridge have been carefully positioned into place using a 75-metre-high crane with a jib length of 114 metres. The first section of the bridge, the land-based part of the bridge, was manoeuvred into place on Sunday, November 30, followed by the second part on December 2. The third section was lifted into place on Sunday, December 7, and the fourth then lifted into place on Monday, December 8.
The next phase of work
With the bridge structure now in place, the next phase focuses on completing the decking and panelling, installing handrails, and removing scaffolding. Surrounding works will also take priority, including masonry enhancements and parapet installation to ensure safe and seamless access.
Lighting will play a key role in the bridge’s design, with power and connections set to be installed in early 2026. The lighting scheme has been carefully planned to complement the bridge and its natural surroundings while minimising impact on local wildlife.
Gavin Hulme, Civil Engineering’s Managing Director said: “Reaching this point in the project is a very proud moment for our whole team and this it’s been great to deliver monumental project with Preston City Council. The seamless lifting of all four bridge sections was a demonstration of the precise engineering and dedication of everyone involved in delivering infrastructure that will serve the local community for generations.”


The background
The ‘Old Tram Bridge’ - connecting Avenham Park in Preston to Penwortham in South Ribble - closed unexpectedly in February 2019 amid fears it could suddenly collapse after a series of serious defects were uncovered - and it was eventually demolished last summer, in half the time expected, due to its poor state.
Preparation work for the latest iteration of the bridge - which has been in place in various forms since 1804 - has been under way ever since.
The replacement Tram Bridge has been delivered by Preston City Council using part of its £20 million grant awarded by the UK Government, with an additional £1 million from Lancashire County Council.