18-year plan for Penwortham's 920-home site revealed - here's where & when work will begin
The last unit is set to be completed in 2044.
A plan of where and work will begin on Penwortham’s Pickerings Farm development has been released - and it’s set to go on for 18 years.
It was ratified by SRBC in 2024, with the total number of homes being altered to ‘up to 920’. As well as houses, the plan also includes the building of a local centre including retail, employment and community uses, a two-form entry primary school, and green infrastructure.
Now joint applicants, Homes England and Taylor Wimpey, have applied to fully discharge condition three of the planning permission - related to phases of building.


A plan shows the land - to be called The Lanes - divided into five sections:
Section 1 (red) - Infrastructure work with no units, running from November 2027- October 2029
Section 2 (orange) - 453 units to be delivered between April 2029- March 2038.
Section 3 ( yellow) - 197 units to be delivered between November 2032- January 2038.
Section 4 (purple) - 201 units to be delivered between April 2037-June 2044
Section 5 (green) - 39 units to be delivered between April 2037-January 2039.
At the time of the approval, Graham Eastham of Keep Bee Lane Rural (KBLR) said members were “gutted”, as the site was ‘the last bit of green space between the distinct communities of Penwortham and Lostock Hall’, and vowed to continue to hold the developers’ feet to the fire as they finally set about making their vision for the site a reality.
SRBC planning bosses will make a decision on whether to agree the suggested phasing within coming weeks.