M56 to close for weekend in September as project to upgrade the motorway finishes up in Cheshire
and live on Freeview channel 276
National Highways has been adding an extra lane and technology on the M56 between junctions 6 (Hale) and 8 (Bowdon).
The agency said this will “help smooth drivers’ journeys through a section of the network carrying up to 100,000 vehicles a day.”
Advertisement
Hide AdAdvertisement
Hide AdAs part of a key phase of work, the motorway will be totally closed from 9pm on Friday (September 9) to 6am on Monday (September 12).
Where will the closure be?
The eastbound carriageway will be closed from junction 9 at Lymm interchange with the M6 to junction 5 for Manchester Airport.
The westbound carriageway will be closed from junction 5 to junction 8 at Bowdon.
“Clearly-signed diversions will be in place,” a spokesman for National Highways said.
Will the closure affect access to Manchester Airport?
National Highways said they have worked closely with Manchester Airport throughout the project and access to the airport will be maintained – via the westbound M56 at junction 5 – throughout next month’s weekend closure.
Advertisement
Hide AdAdvertisement
Hide AdHolidaymakers with overnight flights and heading to the airport from places like the West Midlands, north Cheshire and North Wales will be able to use a motorway diversion from junction 9 of the M56 at Lymm or a local diversion from junction 7 at Altrincham.
During the weekend closure, access to Manchester Airport at junction 5 will be maintained via the westbound M56.
A westbound diversion will operate using the M60, M62 and M6.
Drivers from the Midlands and North Wales planning to use the eastbound M56 to head to the airport or Manchester city centre will need to use the M6, M62 and M60 diversion instead.
Advertisement
Hide AdAdvertisement
Hide AdDrivers are also being advised the westbound carriageway will be closed at times - between junction 5 and junction 7 - during the preceding weekend from 9pm on September 2 to 6am on September 4 and again from 9pm on September 4 to 6am on September 5.
Access to the airport at junction 5 will be open at all times but a good motorway diversion away from the westbound M56 will be in place for other drivers.
What work will be carried out during the closure?
Work during the closure will include:
- installation of manhole covers ahead of surfacing work
- continuing installation of stopped vehicle detection (SVD) on westbound and eastbound carriageways
- completion of concrete central safety barrier
- re-surfacing sections of the carriageways
- resurfacing the slip roads at junction 6
- restoring traffic counting safety ‘loops’ in the carriageway
Advertisement
Hide AdAdvertisement
Hide Ad- painting emergency areas orange so they are visible to drivers
- installing new lighting columns in the central reservation
- removal of temporary safety barrier and other traffic management measures
What have National Highways said about the closure?
“The four-mile section of motorway between junction 6 at Hale and junction 8 at Bowdon is part of the important corridor between Manchester and Manchester Airport and the Midlands,” a spokesman said.